These are the 4 757’s that will be outsourced to TIMCO.
Acft Fleet Subfleet Dock Span Start Finish
5CK |
757 |
75W |
OS1 |
38 |
11/1/2011 |
12/9/2011 |
5CL |
757 |
75W |
OS1 |
38 |
12/10/2011 |
1/18/2012 |
5CP |
757 |
75W |
OS1 |
36 |
1/19/2012 |
2/23/2012 |
5CM |
757 |
75W |
OS1 |
36 |
2/24/2012 |
3/30/2012 |
|
|
|
|
|
|
|